Pluto LNG start-up delayed to 2012 as costs overrun
Publication date: 17 June 2011
Gas Strategies Group
10 Saint Bride Street
London UK
EC4A 4AD
ISSN: 0964-8496
Twitter @GasStrategies
Editorials
Subscriptions
The first scheduled LNG cargo from the 4.3mtpa Pluto LNG project in Western Australia will not leave the liquefaction plant until March visual_editor01visual_editor, six months later than last scheduled, operator Woodside Petroleum announced today. The company cited “slower than expected” progress on the commissioning of the onshore gas plant and seven weeks of adverse weather as the reasons for the delay.